  • Bug fixes, UI polishing, and performance tuning post-1.0 beta delivery of the system in phase-3.

    Due by September 22, 2017
    37/37 issues closed
  • Formal feedback on Phase 1 from CDOS. CDOS contractual acceptance depends on addressing these issues, per 8/25 CDOS email.

    No due date
    6/6 issues closed
  • Corresponds (per conversation in early September between DS and SS) to the contractual Second System Deliverable in (the expected) Amendment 2. By other methods of reckoning, this is the 3rd iteration of CORLA system, after round 2 of user acceptance testing.

    Due by September 15, 2017
    175/175 issues closed
  • 2nd iteration of CORLA system, after round 1 of user acceptance testing.

    Due by August 25, 2017
    92/92 issues closed
  • Initial implementation of CORLA system.

    Due by August 17, 2017
    108/108 issues closed