You signed in with another tab or window. Reload to refresh your session.You signed out in another tab or window. Reload to refresh your session.You switched accounts on another tab or window. Reload to refresh your session.Dismiss alert
I am getting a gross overestimation in concrete column volume for a project. I do not see the quantity of concrete in question anywhere in the project. There are two Column Categories, one is the correct volume and one is roughly 40x that value. I think it has to do with the project elevation being in the range of 2000' for the base level, possibly the analysis is assuming everything is extended to zero? The internal calculations Revit provides for material volume are accurate.
The text was updated successfully, but these errors were encountered:
Update, I reset the shared coordinates so that the elevation of my first slab was closer to an origin point of 0,0,0 instead of +2000 z, and an x, y, miles from 0, 0, and this seemed to fix my issue.
I am getting a gross overestimation in concrete column volume for a project. I do not see the quantity of concrete in question anywhere in the project. There are two Column Categories, one is the correct volume and one is roughly 40x that value. I think it has to do with the project elevation being in the range of 2000' for the base level, possibly the analysis is assuming everything is extended to zero? The internal calculations Revit provides for material volume are accurate.
The text was updated successfully, but these errors were encountered: