Comments
Due date being revised in light of new US plan form construction and commissioning. See Change Request C023. |
Change Request C023 approved at 25/MAY/21 Exec Group. This moved the due date for MS12 from 30/APR/21 (PM22) to 30/JUN/23 (PM48). |
16/NOV/22
|
Exec meeting on 28/NOV/22 approved Change Request C057 that stated this milestone corresponds to the Rubin Project supporting milestone : "COMC-0140 : Begin Science Verification". According DMTN-232 dated 05/JAN/23, the due date is 07/JUN/23 (LSST:UK PM48). |
12/JUL/23
|
24/AUG/23
|
06/JUN/24
|
Change Request C057 states this milestone corresponds to the Rubin Project supporting milestone : "COMC-0140 : Begin Science Verification". See https://dmtn-232.lsst.io/ for due date of this.