-
Notifications
You must be signed in to change notification settings - Fork 10
/
Copy pathORNL-CF-70-2-7.txt
1453 lines (992 loc) · 52 KB
/
ORNL-CF-70-2-7.txt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
892
893
894
895
896
897
898
899
900
901
902
903
904
905
906
907
908
909
910
911
912
913
914
915
916
917
918
919
920
921
922
923
924
925
926
927
928
929
930
931
932
933
934
935
936
937
938
939
940
941
942
943
944
945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
K S
OAK RIDGE NATIONAL LABORATORY
OPERATED BY For Internal Use Only
UNION CARBIDE CORPORATION
NUCLISION 0 R N L
CENTRAL FILES NUMBER
OAK RIDGE, TENNESSEE 37830
™ - 2 - 7
DATE: February )_;’ ]_970 COPY NO. 51
SUBJECT: Tritium in the MSRE:
Calculated Production Rates and Observed Amounts
TO: R. B. Briggs
FROM: P. N. Haubenreich
ABSTRACT
Tritium was produced by the interaction of neutrons with lithium in
four regions of the MSRE: the fuel salt, the thermal insulation around the
reactor vessel, the treated water in the thermal shield and instrument shaft
and the coolant salt. Production rates calculated for each region are
respectively about 40, 3, 0.005, and 0.001 curies per full-power day of
operation with 23U fuel. During £3°U operation the thermal neutron flux
in the fuel was lower and the tritium production from lithium in the fuel
was about 2L curies/day. Tritium was also produced in the fuel as a fission
product at a rate of 0.1l curie per full-power day.
5
During the last two power runs of the MSRE, while the reactor was at
full power, tritium concentrations were measured in the fuel salt offgas,
the coolant salt offgas, the air in the containment cell, and air that had
passed across the radiator tubes. Discharge rates in the fuel offgas came
up to about 25 curies/day; in the coolant offgas, 0.6 curie/day; in the cell
air, about 0.0l curie/day; and in the radiator cooling air, around L4 curies/
day. 1In addition, tritium was removed in condensate from the containment
cell atmosphere during long periods of operation at rates around 4 curies
per full-power day,
Keywords: +tritium, fused salts, reactors, reactor safety, operation.
NOTICE This document contains information of a preliminary nature
and was prepared primarily for internal use at the Oak Ridge
National Laboratory. It is subject to revision or correction and
therefore does not represent a final report. The information is
only for official use and no release to the public shall be made
without the approval of the Legal and Information Control Depart-
ment of Union Carbide Corporation, Nuclear Division.
CONTENTS
ABSTRACT ©. & &4 ¢ o ¢ o o ¢ o o o o
INTRODUCTION .
CALCULATED PRODUCTION RATES. . . .
Fission Product . . . . .
Lithium in Fuel Salt .
Coolant Salt. . . . . . . . .
Thermal Insulation around Reactor
Treated Water System. . . . .
OBSERVED AMOUNTS .
Containment Cell Condensate .
Accumulation in Treated Water .
Fuel Salt Offgas.
Coolant Salt Offgas . . . . .
Containment Cell Exhaust.
Radiator Cooling Air
SAFETY CONSIDERATIONS. . .
CONCLUSIONS. . . . . .
APPENDIX . . . ¢ 4 ¢« o o « ¢ o o &
Vessel.
J
oy
M
«J\n\n\ni—‘lfll
11
12
13
13
13
18
18
2l
2l
25
31
32
35
INTRODUCTION
It was recognized before the MSRE was ever operated that substantial
amounts of tritium would be produced and that most, if not all, of it
would probably be released through the stack. The calculated concen-
trations at ground level were so low, however, that when power operation
began, no effort was made to verify the predicted tritium release rates,
Tritium appeared in liquid wastes and was treated with the proper health
precautions, but no great effort was made to clear up uncertainties as
to its origin. In the summer of 1969, however, serious attention began
to be given to problems of tritium containment in large molten-salt power
reactors. This led to efforts to determine, in the last few months of
power operation, where the tritium produced in the MSRE was going. As
indicated in Fig, 1, there were several regions and paths to be considered.
This report describes the calculations of tritium production and the
observations that were made at the MSRE. The intent is to make this in-
formation available in a convenient form for use in connection with
transport calculations that are being made by others and will be reported
elsewhere,
CAICULATED PRODUCTION RATES
F'ission Product
Tritium is produced as a product of three-way (ternary) fission of
uranium at a rate of about one atom per 10% fissions.! At 8 Mw(th) and
a yield of 1 x 10™4 atom/fission, the production rate by this mechanism
is 0.1 curie/day, all in the fuel salt.
p———
1D. G. Jacobs, Sources of Tritium and Its Behavior upon Release to
the Enviromment, USAEC Critical Review, TID-24637 (December 1968) p. 1k,
t ORNL DWG. T0-1589
VENTILATION f
STACK
P . oo
® I {k\
FUEL SALT | COOLANT SAT s
OFF GAS '] OFFaAs
SYSTEM ~ SYSTEM
HELIOM |
LITHIUM . FUEL SALT CCDLSQ:&S:LT I_/\/\i; j
VS S
IN FUEL. SALTaqp”l SYSTEM | HVK . RADIATOR
1
TURES
i —
TuBES }\_
{anun IN
COOLANT SALTY D —
LTttt N
\WOSVULATION
- PIPING
LiTrHioM N
GAS
CORRASION WN CELL
VN HI 3\TOQ ! ] g ATMOSPHERE RN \
A ] O‘ST.\"?‘ LIQUID WASTE
TREATED N CELL CYSTEM
WATER ATMOSPHERE " '
oYSTeEM @
v 5
0 >'/ CONDENSATE
FROM CCP COOLER
OS CLINCH
~.. RWER \\ .
MOSKRE \ SO
LIQUID WASTE ~—_ ~
TANK \\\ ™
oL G
Fig. 1 Tritium Production and Transport in MSRE
(s
Lithium in Fuel Salt
Each neutron absorption in °Li produces a tritium atom,.
6Li + In - *He + =H
The cross section for this reaction is quite large for thermal neutrons
(L76 b for the thermal neutron energy spectrum in the MSRE core). Fast
neutrons can also react with “Li.
71i + n - 4He + °H + 1n
This reaction is far less probable than the °Li reaction, however, because
its threshold energy is 2.8 Mev and the cross section reaches a maximum
of only 0.4L4 barns at 7.5 Mev, |
The lithium in the MSRE salts contains less than 0.01% °ILi, but,
because of its large reaction cross section, this isotope is responsible
for over 80% of the tritium production., This means that: (1) the actual
production rate changes in almost direct proportion to changes in the o11
content of the salt, and (2) an accurate prediction of tritium production
depends on an extremely accurate assay of the lithium. .
The ®°Li content of the lithium going into the MSRE was established,
with a high degree of confidence, to be less than 0.01%. To begin with,
the lithium was selected from stockpiled LiOH in which the ©ILi had been
depleted to 0.01% or less. Assays which were available for each batch
of LiOH formed the main basis for selection,® 2 Then, after conversion
of the hydroxide to LiF, the lithium in each product batch was again as-
sayed before the LiF was used to make up coolant, flush, or full carrier
salt, Each container of salt loaded.into the MSRE was identifiied as to
the LiF batch used in its preparation.
P, N. Haubenreich, Selection of Lithium for MSRE Fuel, Flush and
Coolant Salt, MSR-62-34, April 10, 1962.
“H., F. McDuffie, Selection of 7“Li Batches for MSRE Fuel, Flush, and
Coolant Salt, MSR-62-41, May 22, 1962.
The criticality calculétions for the MSRE had to be done before the
salt production was finished and for this reason the ®11i fraction was
taken to be the average for the LiOH batches that were scheduled to be
used, The assays for the batches obtained for the MSRE ranged from
0.0072% to 0.0085% ®Li. The average of the batches which were to be used
for the flush salt and the fuel carrier salt was 0.0074%. This value was
used for the initial criticality calculations and was the starting point
in the calculations of long-term reactivity effects due to °Li burnout.
It has also been used up to the present in the calculation of tritium
production rates,
The most refined, most recent neutron-balance calculations for the
MSRE are the result of using the GAM-II, THERMOS, and EXTERMINATOR pro-
grams with the ENDF/B cross sections. All neutron absorptions in °Li
are assumed to produce tritium; the tritium production from 71i is com-
puted from the high-energy fluxes and the cross-section for this specific
reaction., Results of these calculations, assuming 0.0074% ®ILi in the
lithium are given in the first column of Table 1 (Ref. 4). 1In the
operations with 233 as the principal fissile material, the fissile ma-
terial concentration was much lower, the thermal neutron flux much higher
and the fast neutron flux about the same as in the 272U operation, These
differences account for the changes in tritium production rates from
2355 to 233 operation.
The rates in the second column of Table 1 are simply the equivalents
of the yields in column one, calculated for a power level of 8 Mw and
200 Mev/fission recovered energy.
There is good reason to believe that the ©Li assay of the lithium
in the MSRE was not exactly 0.0074% and that the full power of the MSRE
was less than 8,0 Mw, The last two columns of Table 1 are based on values
arrived at as described in the paragraphs which follow,
The ®Li fraction in the lithium in the MSRE fuel salt was not meas-
ured by sampling either the salt in the reactor or the salt mixtures that
“B. E, Prince, personal communication.
oy
Table 1
Some Calculated Rates of Tritium Production
From Lithium in MSRE Fuel Salt
0.0074% ®Li, 8 Mw Varying6Li,(a) 7.25 Mw
Fuel Source atoms/10* fissions curies/day atoms/lo4ffissions curies/day
o1i 303 32 210 20
2 .35U
‘Li b7 5 b7 l
350 37 - 257 2L
233 "I 56T 29 371 35
714 57 6 57 >
624 65 428 Lo
“Numbers listed for 23U assume 0.0051% SLi; for 233U operation,
0.0048% ®1i. These values are based on 0.0055% 1i at start of operation,
decreasing due to burnup for 65,300 Mwh and 95,500 Mwh.
10
were loaded, The fraction at the beginning of power operation must be
inferred, therefore, from the assays that were made on the LiOH feed
material and, at an intermediate step in the salt production, on the LiF
before it was mixed. The significant depletion of the 61i due to burnup
during high-power operation must also be calculated,
The assays on the batches of LiF used to make up the fuel salt ranged
from 0.004% to 0.006% ®Li and averaged 0.0049% (Ref. 5). This is ap-
preciably less than the 0.007T4% average of the assays on the LiOH from
Which the LiF was prepared. The two sets of measurements are believed
to be of equal reliability and accuracy. It seems impossible, hbwever,
that the ®Li content actually decreased, so the difference must be due
to some analytical bias. Since the MSRE lithium had the lowest °Li
fraction of any lithium around, contamination of the samples in handling
or analysis would tend to make the ®Li assay erroneously high, It seems
reasonable, therefore, to conclude that the lower set of values is prob-
ably nearer the actual ®ILi fraction in the LiF that went into the fuel
salt mixture.
The ®Ii fraction in the fuel salt mixture would be higher than that
in the LiF feed because of introduction of a small amount of natural
lithium as a contaminant in the BeF,. The BeF, for the MSRE salts was
purchased with a specification of <50-ppm Li and analyses showed only
that Li was less than 50 ppm. If one assumes that the BeF, contained
50-ppm natural Li, the ®Li fraction in the fuel salt lithium would be
increased by 0.0013%.
Thus one must conclude that the ©Ii fraction in the fuel salt at
the beginning of power operation could have been as high as 0.0087%
(assuming 50-ppm Li in the BeF, and using the LiOH assays) or as low as
0.0049% (assuming very little ILi in the BeFs and using the LiF assays).
The most likely value was probably between 0.005% and 0.006%. A value
of 0.00SS% ®1i at the beginning of power operation was assumed in ar-
riving at the tritium yields in the last two columns of Table 1,
°J. H. Shaffer, personal communication.
11
The operation with £2°U amounted to 9006 equivalent full-power hours
(EFPH). If, as nuclide changes indicate, the full power was T.25 Mw, the
operation burned up about 4,9% of the 235U and about 6.8% of the °Li.
After the 72U was loaded the reactor operated another 4166 EFPH, burning
L.3% of the 233U and another 5.6% of the °Li. Starting at 0.0055% the
®Ii would be down to about 0,0051% at the end of £7°U operation and
0.0048% at the final shutdown.
Of the different figures in Table 1, it now appears that those in
columns 3 and 4 probably are nearest the actual production rates of
tritium in the fuel salt.
Coolant Salt
During power operation the coolant salt is exposed to neutrons in
the primary heat exchanger; there it is in close proximity to the fuel
which 1s emitting delayed neutrons and a few fission neutrons., Because
the thermal shield absorbs most of the neutrons leaking from the reactor
vessel, the exposure of the coolant salt to neutrons other than in the
heat exchanger is negligible,
The coolant salt activation in the heat exchanger was computed in
1962, using TDC, a multigroup neutron transport code, The calculations,
which were for a delayed neutron source appropriate for ] fuel, gave
neutron absorption rates in ®Li and “"Li of 0.42 x 101° and 0.15 x 101°
per Mw-sec (Ref. 6). Even if all the absorptions in “Li produced tritium
(whiéh they do not) the corresponding total production rate is only
0.17 x 1072 curie/day at 7.25 Mw, With 3% fuel the delayed neutron
source is less by about a factor of two and the tritium production is
accordingly less, The production rate in the coolant salt in this case
is about 0.1 x 10”2 curie/day or less.
' ©P, N, Haubenreich and B. E, Prince, Calculated Activation of
Flinak and LiF-BeF, Salt in MSRE Coolant System, CF-62-11-96,
November 29, 1962,
12
Thermal Insulation around Reactor Vessel
Between the reactor vessel and the thermal shield is a layer of
thermal insulation 5-in, thick, The insulation, Careytemp 1600, contains
trace amounts of lithium (natural) and is subjected to a rather high
neutron flux so there is some tritium produced in it.
A large uncertainty in the calculated tritium production arises be-
cause of uncertainty in the lithium concentration in the insulation actu-
ally installed, A sample of the material that was to be used at the re-
actor was analyzed by a semi-quantitative spectrographic technique in
December 1962. Lithium was reported as 0.1%. For this type of analysis
the actual value should be within the range from one-half to twice the
reported value. This analysis would therefore indicate a concentration
of 500 to 2000 ppm Li in the insulation which went into the reactor. In
June 1966, when tritium was detected in the reactor cell after power
operation, the installed insulation was inaccessible, Samples of Carey-
temp 1600 from 3 boxes of new stock were analyzed for lithium by flame
photometry of material leached with HC1l. Results were L4, 13, and 4 ppm
Li. The reason for the difference by a factor of roughly 100 has not
been resolved.
The neutron flux in the insulation is fairly well defined by measure-
ments that were made with flux monitors between the reactor vessel and the
insulation.” The average thermal neutron flux in the T9-ft> of insulation
on the sides was measured to be about 7 x 10'° n/cm®-sec-Mw; in the 35 £t~
on top and bottom, about 4 x 10° n/cm*-sec-Mw, using 8 Mw as full power,
The thermal neutron cross section for ©Li that is consistent with these
measurements is 458 b,
The density of Careytemp 1600, according to the manufacturer's hand-
boock, is 10 lb/ft3. Using the foregoing volumes, fluxes and cross section
and assuming 1000-ppm natural lithium in the insulation, the tritium pro-
duction rate was calculated to be 3.0 curies/day at full power from thermal
"MSR Program Semiann. Progr. Rept. Aug. 31, 1968, ORNL-434L4, pp. 19-22, -
13
neutron absorption in ©1i. Production from “ILi would be far less because
of the abundance (7.4%) of °Li in the natural lithium,
Considering the uncertainty in the lithium content of the insulation,
one can say only that the tritium production in the insulation is probably
less than 6 curies/day and is conceivably less than 0.l curie/day,
Treated Water System
The water which circulates through the thermal shield and within the
instrument shaft contains lithium nitrite as a corrosion inhibitor. The
LiNOs was especially prepared from lithium depleted to <0.01% ®Li to mini-
mize tritium production. Nevertheless because some of the water is in a
high neutron flux near the reactor vessel, there is some tritium production.
The average thermal neutron flux in the 4000-gal circulating treated
water system was estimated on the basis of the activation of the potassium
in the original corrosion inhibitor to be about 7 x 10° n/cm®=-sec-Mw (Ref. 8).
The 1lithium concentration hes been held at about 0.20 mg/mg. Assuming a
®1i fraction of 0.01% and a ®1i cross section of 900 b (appropriate for
thermal neutrons at the water temperature), the tritium production in the
circulating system is calculated to be 5 me per full-power day.
OBSERVED AMOUNTS
Containment Cell Condensate
In the summer of 1966, a few weeks after the reactor contaimment cell
was sealed and power operation started, water was found in the piping at
the component cooling pumps. (The pumps, located in containmment vessels
in the Special Equipment Room, recirculate gas from the reactor cell
through freeze valve and pump bowl shrouds.) The tritium concentration
in this water was about 1 mc/mz.' Water continued to accumulate at the
component coolant pumps at a rate of roughly a gallon per day but none
8MSR Program Semiann. Progr. Rept. Feb. 28, 1966, ORNL-3936, p. 29.
14 | .
appeared in the sumps in the reactor cell or fuel drain cell, Apparently “
water leaking somewhere in one of the cells was evaporating before reaching
the sump, and this atmospheric moisture was condensing in the coolest part
of the recirculating system. The tritium concentration in the condensate
was higher than that in the treated water system by a factor of about
50,000, so an additional source of tritium in the cell was indicated.
Production in the thermal insulation around the reactor vessel was the
suspected source,
Despite efforts to locate and stop the water leakage into the cell,
the same situation persisted throughout the operating history of the re-
actor, i.e., tritium-laden moisture always began condensing in the com-
ponent cooling system a few days after the cells were sealed. A drain
line and condensate collection tank were installed so the condensate could
easily be measured and transferred periodically to the 11,000-gal. Liquid
Waste Tank. This in turn was emptied into the Melton Valley waste system
at intervals of several months. The tritium inventory in the Waste Tank,
as indicated by samples before emptying and occasional other samples, is s
therefore a means of determining averagé rates of removal of tritium from
the reactor cell in the condensate.
The pertinent information on tritium in the Waste Tank is plotted in
Fig. 2, Each tritium inventory indicated by a circle is the product of
sample analyses (usually of two duplicate samples) and the measured volume
of liquid in the tank at the time., The crosses represent tritium inven-
tories based on earlier analyses and the measured heel left after a trans-
fer out of the tank,
Inspection of Fig. 2 shows that probably the most reliable values for
tritium accumulation rate can be obtained from the changes during three
selected intervals: 10/66 - 9/67, 9/67 - 3/68, and 1/69 - 7/69. The
data on the tritium in the waste tank during these periods are summarized
in Table 2, As indicated in the table, the average rates of accumulation
of tritium in the tank during the three periods were 0.1h4, 0.23, and
0.19 curle/EFPH. It may be noted that not quite all the tritium-laden
moisture in the cell atmosphere reaches the waste tank: each time the
cell is vented after the end of a run, the moisture in the cell is swept
.
~
-/
IN WASTE TANK (Cum'E
TRITIUM
1
Accumulation of Tritium in MSRE Liquid Waste Tank
ORNL DWG.
0-1590
a1
16
Table 2
Accumulation of Tritium in Idiquid Waste Tank
During Selected Periods of Operation
PERIOD
I II IIT
Start
Date 10/26 /66 9/3/6T 1/26/69
Integrated Power (EFPH) 1325 5567 9148
Before transfer
IW volume (gal) 8850 6750 7900
IW tritium (curies) 23% 588° 96"
After transfer
LW volume (gal) 160 1450 900
IW tritium (curies) 0.k 126 11
End
Date 8/2L /6T 3/31/68 7/8/69
Integrated power (EFPH) 556T 9006 11,555
IW volume (gal) 6500 7100 - 7400
IW tritium (curies) 588 908 L7l
Change
IW tritium (curies) 588 782 L60
Integrated power (EFPH) Lol? 3439 2LOT
Rate (curies/EFPH) 0.139 0.227 0.191
“Extrapolated from inventory at 1262 EFPH (10/23/66) at 0.2 curie/EFPH,
P pssumed no change since inventory on 8/2k /67 (fuel in drain tanks,
closed in interim),
“Extrapolated from inveotory at 9007 EFPH (1/10/69) at 0.2 curie/EFPH.
t(w
L7
out, Based on the observed dewpoint in the gas cooler, the amount of
moisture in reactor and drain tank céll atmosphere at any time was about
32 1b of water., Condensate samples averaged 1350 uc/cc, so the amount of
tritium carried out each time the cell was opened was 20 curies. The
cell was opened 3 times during the first period in Table 1 and once each
during the other two periods., Adding 20 curies for each opening gives
rates of appearance of tritium in cell moisture of 0.15, 0.23, and
0.20 curies/EFPH (3.7, 5.6, and 4.8 curies per full-power day).
An independent check on the collection rate during Period I can be
obtalined from measured condensate collection rates and tritium concen-
trations in the condensate observed during Runs 11 and 12 (Ref. 9).
During both those runs the condensate rate was about 0.9 gal/day. A
condensate sample in Run 11 at full power showed 1,28 mc/cc; one in Run 12
showed 1,22 mc/cec, These correspond to 4,3 and 4,1 curies per full-power
day, slightly higher than the 3,7 obtained from the waste tank data in
Period I, In October 1969, a sample of the condensate was taken midway
of an 8-day period at full power over which 3.9 gal, accumulated. The
tritium concentration was 1,56 mc/cc, corresponding to a collection rate
of 2.9 curies per day, considerably less than the rate indicated by the
waste tank accumulation over the longer interval of Period IIT.
During Periods I and II the reactor was operating on 27°U; during
Period III, =33, It appears that the data are not good enough to dis-
tinguish any difference due to the change in fissile material, i.e., if
there was a difference it was small relative to the probable error in the
measurément. The calculated tritium production in the salt increased by
about TO percent when the change to 37U was made. On the other hand,
the production in the thermal insulation probably changed much less be-
cause it was due mainly to neutrons that leaked from the reactor with
epithermal energies., This leakage did not increase nearly as much as did
the thermal neutron flux in the core. Thus there is a suggestion that
the tritium in the cell came largely from the insulation rather than from
the salt. The observed rates are within the upper end of the range of
calculated production in the insulation (3 #* 3 curies/full-power day).
°MSR Program Semiann. Progr. Rept. Aug. 31, 1967, ORNL-4191, pp. 34-35.
18 i
Accumulation in Treated Water .
Between May 1966 and November 1969 a total of 35 samples from the
treated water system were analyzed for tritium. Results, converted to
tritium inventories in the 4000-gal. system, are shown as points in Fig. 3.
The line was computed using the simplified representation of the reactor
power history, the calculated tritium production rate of 2.1 x 10~ *
curie /EFPH (5 mc per full-power day), and a dilution rate due to water
makeup of 1% per month. The agreement indicates that the calculated
production rate is reasonably close to the actual rate. i
Fuel Salt Offgas
In the safety analysis of the MSRE (discussed in a later section) it
was assumed that all of the tritium produced in the fuel would leave by
way of the fuel offgas system. Because the dispersal of tritium through
the stack provided a large margin of safety and because there were no o
suitable instruments for continuous monitoring of tritium mixed with a '
very high concentration of fission products, no attempt was made to
measure the tritium in the fuel offgas until the autumn of 1969. During
that summer the problem of tritium in large molten-salt reactors began to
receive serious attention. Calculations indicated that the tritium
originating in the fuel salt would not all leave in the fuel offgas, but
that a substantial fraction would diffuse through the metal walls. It
was determined therefore to make the effort necessary to measure tritium
in the gaseous effluents from the MSRE during the brief period of opera-
tion still remaining.
To measure the tritium in the fuel offgas, analytical chemists de-
signed an apparatus that could be connected downstream of the charcoal
beds, where the fission product activity was low enough to permit direct
operations, The apparatus consisted essentially of a heated bed of cop-
per oxide followed by refrigerated traps to collect the moisture produced
by reaction of tritium and hydrogen with the CuO (Ref. 10). The moisture
*°J. M. Dale, Tritium in the Effluent Gases of the MSRE, internal
memo MSR-70-9 (Jan. 30, 1970).
1966
Fig. 3
1967 968
Buildup of Tritium in MSRE Treated Water System
ORNL DWG, T0-1591
1969
6T
20
was then removed to a laboratory for measurement of the amount of tritium
collected from a measured volume of gas passed through the sampler.
Samples run with the Cu0 at different temperatures would provide some
information on the form in which the tritium was found, With the Cu0 at
3k0°C, To (or HT) would react to form water and be collected, At 640°C
the CuO would react with most hydrocarbons but not with methane, and at
800°C it would react with methane also. This system was ready in October
and was installed then in the MSRE venthouse.
After leak-testing and checkout of the tritium sampler, the first
analysis on the fuel offgas was obtained on October 2L, At that time,
as shown in Fig., 4, the reactor had been operating steadily at full power
for 21 days and the gas flow through the fuel offgas system had been
steady at 4.2 z/min of helium for even longer. The first sample was taken
with the CuO at 340°C and indicated that 9.3 curies/day as tritium gas
was passing the sample point, During the next week two more samples were
run with the CuO at higher temperatures. (See Table 3,) At the highest
temperature, which should have collected all the tritium in the sample,
11.3 mc was collected from the 3-liter sample, indicating a total of
22,7 curies/day passing up the stack.
Two days later, on November 2, the fuel was drained and the next day
the helium flow from the fuel pump through the offgas system was reduced
from 4.2 to 2.4 £/min. The core and fuel loop were allowed to cool gradu-
ally to about 450°F, but were kept sealed. On November 21 the fuel offgas
was again sampled for tritium; first with the Cu0O at 340°C, then at 800°C.
As in the earlier samples the CuO at 340°C got about L40% as much tritium
as it did at 800°C., Tritium concentrations were surprisingly high: over
half what they had been in the samples taken with the reactor at power.
The tritium flow up the stack was one-third of what it had been.
Because we had suspected that tritium was being held up in oil resi-
dues (which no doubt liberally line much of the fuel offgas system), we
had proposed early in November to set up to sample the fuel offgas for
tritium at a point near the pump bowl exit. A system for pulling small
amounts of gas from a flange near the pump bowl, through a filter (scanned
by the remote gamma spectrometer) and into the fuel sampler enclosure had
21
a)
ORNL DWG. T0-1592
wn
~
S
\n L
Ava/ s31¥Nno.
wn
oD <+ A O v
NI/
4
s ~
¥3.1/7/ A
22
Table 3
Tritium Content of Fuel Offgas Stream
Downstream of Charcoal Beds
A
Amount of Tritium
Tritium b
CuO Temp Collected Flow
Date °C (me) (curies/d)
Oct. 24 340 4.6 9.3
Oct., 27 640 5.5 11.1
Nov, 1 800 11.3 22,7
Nov. 21 340 2.73 3.1
Nov. 21 800 6.46 Tk
Dec, 2 800 5eTh 11.6
Dec, 2 340 4,79 9.7
Dec. 11 800 T 46 15.0
340 15.29 30.8
Dec., 12
aFro:m a 3-liter sample.
bIn the helium stream past the sample point,
Helium flow was 4.2 liters/min. except for Nov. 21
when it
was 2.4 liters/min,
23
already been designed for installation around the end of November and
we proposed to add to it a sample line coming out of the containment
which could be used to withdraw gas samples for tritium analysis, On
November 18, however, a management decision was reached that because of
insufficient funds the plans could not be carried out. A brief run was
authorized, however, with one of its goals to obtain as much information
as possible on tritium within the limitations of time and money.
On November 22 the helium flow was restored to 4.2 g/min., on
November 25 the core was filled with fuel salt and on November 26 the
reactor was taken to full power for the final run, Six days later an-
other pair of samples was taken with the CuO at 340°C and at 800°C. The
tritium concentration indicated by the 800°C sample was slightly less
than in the sample during the shutdown but, because of the increased
helium flow, the rate to the stack was up. The tritium flow to the stack
was still only half what it had been at the end of the previous power
run, however., Another difference was that the fraction reacting with
Cu0 at 340°C was over 80% of that reacting at 800°C.
For the next ten days the tritium sampling apparatus was occupied
with the effort to establish the amount coming out of the radiator. On
the afternoon before the final shutdown, a fuel offgas sample drawn
through 800°C CuO indicated 15 curies/day passing the sample point. The
next morning with the CuO at 340°C, an amount equivalent to 31 curies/day
was collected, This was the last sample, By the time the anomaly was
fully appreciated, the system had been shut down and flow through the
offgas system stopped.
While the fuel was circulating in Run 20, a total of 26 samples were
taken from the fuel-pump bowl (plus three additions of beryllium and two
of uranium)., Among these were 10 sampling devices aimed at obtaining
some measure of the tritium in the sampling enclosure in the pump bowl,
These consisted of nickel capsules filled with copper oxide, copper
oxide and palladium, and nickel powder and solid bars of nickel, all ex-
posed for 8 to 12 hours in the gas space of the pump bowl. As of this
writing these samples had not been analyzed.
2l
Coolant Salt Offgas
Calculations of the possible distribution of tritium in the MSRE
had indicated that while a significant fraction of the tritium produced
in the fuel system should diffuse through the heat-exchanger tubes into
the coolant salt, very little should go out in the coolant offgas.
Nevertheless, the tritium sampling station was provided with a connection
to the coolant offgas line. Only one sample was taken, This was on
October 30, with the CuO at 800°C and indicated 0.62 curies/day passing
the sample point,
During Run 20, three nickel bars were exposed to the gas in the
coolant pump bowl for 8 to 10 hours, to be analyzed for tritium and com-
pared with similar samples in the fuel pump., Results are not available
at this time,
Containment Cell Exhaust
The reactor cell is kept below atmospheric pressure by continuously
pumping a small stream of gas from the cell through particulate filters
and up the ventilation stack. The flow rate is varied while cell tempera-
tures are changing, but averages about L0 scf/d, Jjust balancing the in-
leakage of gas and intentional input of nitrogen purge into the reactor
and drain tank cell, The exhaust is taken off just downstream of the gas
cooler at the discharge of the component coolant pumps, Here the air is
at 20 psia and the dewpoint is probably about 100°F (the témperafure of
the cooling water in the tubes on which moisture is condensing). For
these conditions there is about 1.0 g of moisture per scf of gas., As
indicated in an earlier section, condensate from the air cooler was found
to contain about 1.5 mc/cc of tritium., Thus the exhaust gas should leave
with about 1.5 mc/scf (0.053 pc/ce) of tritium, At LO scf/d this would
amount to 0.06 curies/day of tritium removed from the contaimment cell.
On October 15, 1969, a 2-ft> sample was drawn from the cell exhaust
line through a calcium chloride bed, which was then counted for tritium.
(This is the standard Health Physics procedure for tritium monitoring.)
25
The tritium on the bed (presumably tritiated moisture collected from the
sample) was equivalent to 9.2 x 10~ ° pne/cc of sample., This is only 17%
of the concentration calculated in the previous paragraph. However, some
moisture undoubtedly condensed and was lost from the stream between the
air cooler and the sampling device. If one assumes that the collected
moisture contained 1.5 mc/g, the sample results would correspond to
6.2 x 10" g of moisture per cc of gas or a dewpoint of 39°F at the
calcium chloride trap. This is lower than one would expect, but not much
lower,
On October 30, a 3-liter sample from the cell exhaust line was run
through the tritium sampling device in the venthouse, with the copper
oxide at 800°C. This sample, which should get all the tritium in the gas
as well as in the moisture, indicated a concentration of only 2.1 x 10~
uc/cc. This seems extraordinarily low, both by comparison with the esti-
mate and with the sample taken on calcium chloride.
Radiator Cooling Air
Because the relatively large area and thin walls in the heat ex-
changer and radiator tubes offer a rather low-resistance escape path, a
substantial fraction of the tritium produced in the fuel salt would be
expected to find its way through the coolant salt system and into the